Court told ex-Tepco Execs were informed barriers could prevent tsunami flooding at Fukushima plant

Fukushima 311 Watchdogs

Feb 28, 2018
April 2011.jpg
The devastated Fukushima No. 1 nuclear power plant is seen in this April 2011 file photo
 
An employee with a subsidiary of Tokyo Electric Power Company Holdings Inc. testified in court Wednesday that the unit reported a need to install tide barriers to prevent flooding from a tsunami well before the March 2011 nuclear accident at Tepco’s Fukushima No. 1 nuclear plant.
According to the worker, the Tepco unit produced an estimate in March 2008 on the basis of long-term assessments released by a government organization, saying that a tsunami could occur with a height of 15.7 meters, which is above ground level at the nuclear plant site.
The estimate was presented at a meeting in June the same year that was attended by Sakae Muto, a former Tepco vice president.
The worker testified during a hearing at the Tokyo District Court that the Tepco unit…

View original post 220 more words

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s